Abstract:
Because of its contribution to economic development and economic activity, the
construction sector in Ethiopia has a significant impact on national growth. Various studies,
however, reveal that variation of work is one of the key factors contributing to time and
cost overruns, disagreements among parties, rework, and poor work quality. The
fundamental purpose of this research is to identify and analyze the major causes and
impacts of variation of work on public building construction projects in Gondar City. To
achieve the objective of this study, 51 major causes and 14 impacts on the variation of
works were identified, and 22 causes and 12 impacts were refined based on expert
recommendations. The data collection methods used were questionnaire surveys, case
studies, and interviews. A questionnaire survey was used for a total of 135 respondents to
model the cause factors of variation of works using a structural equation modeling
approach through the Analysis of Moment Structure software package. The relative
Importance Index is used to rank the mitigation strategies of variation of works. In
addition, a detailed archive record assessment was carried out to determine the cost and
time implications of the variation of works. For data reduction, identification of factor
structures, and validation of study outcomes, both exploratory and confirmatory factor
analysis methods were applied. According to the research findings, the major causes of
variation of works are change of scope, financial problems, change in specifications, the
inadequate scope of work, inappropriate use of the advance payment, design discrepancies,
differing site conditions, technology change, inflation, and corruption. However, the most
common impacts of variation of work are an increase in project cost, a delay, poor quality,
low productivity, and disputes among professionals. The maximum cost overrun and time
overrun are 59.13% and 690.42%, respectively, as compared to the original contract price
and original contract time. Mitigation measures variation of works are the client should
provide a clear brief of the scope of work, and the consultant should produce a concluding
designs and contract documents. Effective communication between contracting parties
prevents disputes. The study's findings are expected to assist construction organizations,
practitioners, and policymakers in identifying the key factors influencing the variation of
work in the construction of public building projects in Ethiopia.
vi
Keywords: Gondar City, Public Building Projects, Variation of Works, Cause and impact,
Structural Equation Modeling, Factor Analysis